The keel was laid on the USS Enterprise (CVN-80) on April 5th, signifying the beginning of assembly of that ship in dry dock. Fabrication of the ship’s components began on August 21, 2017, with the first cut of steel ceremony.
Launching is schedule for November 2025 with delivery and commissioning scheduled for 2028.
On another note, the USS Gerald R. Ford (CVN-78) FINALLY is ready for deployment. It’s flight deck has been certified and it is expected to go out on its first actual deployment in the fall.
USS John F. Kennedy (CVN-79) launched in 2019 and is expected to be delivered and commissioned in 2024.
I should add that the first cut of steel was held for the USS Doris Miller (CVN-81) on August 25, 2021, but it is not expected to be delivered to the Navy until 2032.
Will be glad to see that proud name returned to the Fleet.
I remember exercises with her predecessor in '83 when she came out of overhaul and was heading to WESTPAC, she was the bait and the Midway sprung the trap and supprised the ■■■■ out of the Russians when we showed up in the Northern Pacific when they thought we were down near Okinawa.
When our fighters flew up to the Bears that went out to recon the Enterprise and they had “U.S.S. Midway” on the sides, they were PISSED.